Duke-897387
2 MW generation in Macon, NC · In queue since June 2023
2 MW
Capacity
1
Components
Hydro
3y 1m
In Queue
Construction
IA Phase
Total Duration
3y 1m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-897387 is a proposed 2 MW hydroelectric generation project located in Macon County, North Carolina. The project is being developed by Duke Energy Carolinas and consists of a single 2 MW hydro component. It is currently listed as active in the Duke Energy Carolinas interconnection queue, with a queue entry date of June 28, 2023. The project's interconnection agreement status is listed as Construction.
The project is located in the Southeast region. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Macon
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
Other
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-897387Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.