Duke-897163
260 MW storage in Wayne, NC · In queue since June 2023
260 MW
Capacity
1
Components
Battery
3y 1m
In Queue
IA Executed
IA Phase
Total Duration
3y 1m
Study Phase
2023 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Commercial operation date not yet determined
Interconnection Agreement executed per LBNL queue status
Duke-897163 is a proposed 260 MW battery storage project located in Wayne County, North Carolina. The project, being developed by Duke Energy Progress, LLC - HF Lee Energy - Storage, entered the Duke Energy Progress interconnection queue on June 16, 2023. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 260 MW of battery storage capacity. It has appeared in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Wayne
Grid Region
Southeast
Market
—
Developer
Duke Energy Progress, LLC - HF Lee Energy - Storage
Utility
Duke Energy Progress
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
LEE SUB - WOMMACK 230KV NORTH
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Duke Energy CHP at Clemson University
Data-driven briefing on Duke Energy — fleet, generation, financial, and news signals.
Analyze Duke Energy's full portfolio
Energy intelligence report generated by Ask.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.