Duke-567168
197 MW storage in Mecklenburg, NC · In queue since June 2022 · Proposed COD December 2029
197 MW
Capacity
1
Components
Battery
4y 1m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2029
Total Duration
7y 6m
Study Phase
2022 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-17
Duke-567168 is a proposed 197 MW battery storage project located in Mecklenburg County, North Carolina. The project, under development by Duke Energy Carolinas, entered the utility's interconnection queue on June 28, 2022. Its interconnection agreement is currently pending.
The project consists entirely of battery storage, with a total capacity of 197 MW. It is interconnected at the HARRISBURG TIE 230 kV point of interconnection.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Mecklenburg
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
HARRISBURG TIE 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-567168Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.