Duke-566542
74.9 MW generation in Darlington, SC · In queue since June 2022 · Proposed COD February 2028
74.9 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Construction
IA Phase
COD target: 2028
Total Duration
5y 8m
Study Phase
2022 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-22
Duke-566542 is a proposed solar generation project with a total capacity of 74.9 MW. The project is located in Darlington County, South Carolina, within the Duke Energy Progress service area. It is being developed by Duke and interconnected to the DOVESVILLE NUCOR 230KV TAP LINE.
The project is listed in the Duke Energy Progress interconnection queue with an entry date of June 29, 2022. The proposed commercial operation date is December 1, 2026, and the interconnection agreement status is currently listed as "Construction".
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
Other
Point of Interconnection
DOVESVILLE NUCOR 230KV TAP LINE
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-566542Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.