Duke-564510
80 MW generation in Bladen, NC · In queue since June 2022 · Proposed COD January 2027
80 MW
Capacity
1
Components
Solar
4y 1m
In Queue
IA Executed
IA Phase
COD target: 2027
Total Duration
4y 7m
Study Phase
2022 DISIS
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-08
Duke-564510 is a proposed 80 MW solar generation project located in Bladen County, North Carolina. The project is being developed by Duke and has an interconnection agreement executed. It is interconnected to the Duke Energy Progress system at the CUMBERLAND - DELCO 230KV point of interconnection.
The project entered the Duke Energy interconnection queue on June 22, 2022, with a proposed commercial operation date of January 8, 2027. The project consists of 80 MW of solar photovoltaic generation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Bladen
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
Other
Point of Interconnection
CUMBERLAND - DELCO 230KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-564510Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.