Duke-324
74.5 MW generation in Gilchrist, FL · In queue since February 2023 · Proposed COD December 2027
74.5 MW
Capacity
1
Components
Solar
3y 5m
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Duke-324 is a proposed solar generation project located in Gilchrist County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Renewable Partners, LLC, is interconnected with Duke Energy Florida via the Hayfield Substation 230 kV. It entered the Duke Energy interconnection queue on February 20, 2023, with a proposed commercial operation date of December 31, 2026. Its interconnection agreement status is currently suspended.
The project consists of 74.5 MW of solar photovoltaic generation. The project's interconnection agreement is also currently suspended.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Gilchrist
Grid Region
Southeast
Market
—
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
Hayfield Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-324Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.