Duke-319
74.9 MW generation in Hernando, FL · In queue since December 2022 · Proposed COD June 2026
74.9 MW
Capacity
1
Components
Solar
3y 7m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
Duke-319 is a proposed solar generation project located in Hernando County, Florida, with a total capacity of 74.9 MW. The project is being developed by Duke Energy Florida, LLC, and is interconnected to the Duke Energy Florida utility.
The project entered the Duke Energy interconnection queue on November 29, 2022, with a proposed commercial operation date of June 1, 2025. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Hernando
Grid Region
Southeast
Market
—
Developer
Duke Energy Florida, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
ERIS
Point of Interconnection
Brooksville-Bushnell East
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Duke Energy CHP at Clemson University
Data-driven briefing on Duke Energy — fleet, generation, financial, and news signals.
Analyze Duke Energy's full portfolio
Energy intelligence report generated by Ask.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
NextEra vs Duke
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.