Duke-273
74.9 MW generation in Polk, FL · In queue since December 2019 · Proposed COD December 2022
74.9 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Construction
IA Phase
COD target: 2022
Total Duration
3 years
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-15
Duke-273 is a proposed solar generation project located in Polk County, Florida, with a total capacity of 74.9 MW. The project, under development by FL Solar 10, LLC, is interconnected to the Duke Energy Florida system at the Tiger Bay Substation 230 kV.
The project entered the Duke interconnection queue on December 17, 2019, with a proposed commercial operation date of October 28, 2022. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
FL Solar 10, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
Tiger Bay Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-273Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.