Duke-258
74.9 MW generation in Highlands, FL · In queue since May 2019 · Proposed COD December 2023
74.9 MW
Capacity
1
Components
Solar
7y 2m
In Queue
Construction
IA Phase
COD target: 2023
Total Duration
4y 7m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
Duke-258 is a proposed 74.9 MW solar generation project located in Highlands County, Florida. The project, developed by Placid Solar, LLC, is interconnected to Duke Energy Florida via the Fisheating Creek Substation 230 kV. It entered the Duke interconnection queue on May 31, 2019, with a proposed commercial operation date of October 28, 2022. The project's interconnection status is currently listed as "Construction".
The development project consists of 74.9 MW of solar photovoltaic generation. It is located in the Southeast region and is listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Highlands
Grid Region
Southeast
Market
—
Developer
Placid Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Service Type
NRIS/ERIS
Point of Interconnection
Fisheating Creek Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-258Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.