Duke-20832
2 MW generation in Marion, SC · In queue since May 2018 · Proposed COD September 2024
2 MW
Capacity
1
Components
Solar
8 years
In Queue
Construction
IA Status
COD target: 2024
Total Duration
6y 4m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-02
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Duke-20832 is a proposed solar generation project with a total capacity of 2 MW, located in Marion County, South Carolina. The project is being developed by Duke and is interconnected to Duke Energy Progress via the Mullins 115kV point of interconnection.
The project is listed as active in the Duke Energy Progress interconnection queue, with an entry date of May 9, 2018, and a proposed commercial operation date of September 2, 2024. Its interconnection agreement status is currently listed as "Construction".
Generated from interconnection queue and public data sources
State
SC
County
Marion
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Mullins 115kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project Duke-20832Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.