CLPT-CLPT G23
150 MW generation in Laramie, WY · In queue since February 2023 · Proposed COD December 2026
150 MW
Capacity
1
Components
Wind
3y 5m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-01
The proposed CLPT-CLPT G23 project is a 150 MW wind generation facility located in Laramie County, Wyoming. The project is being developed by CLPT and is interconnected with Black Hills Cheyenne Light Fuel and Power Transmission. It consists of 150 MW of wind capacity.
The project is currently active in the transmission interconnection queue for the West region, with an entry date of February 20, 2023. The proposed commercial operation date is December 1, 2026. The project's interconnection agreement status is currently in the Facility Study phase, and the point of interconnection is the Bison 115 kV Substation.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Service Type
NRIS/ERIS
Point of Interconnection
Bison 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project CLPT-CLPT G23Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.