CLPT-CLPT G20
365 MW hybrid in Laramie, WY · In queue since July 2022 · Proposed COD December 2025
365 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Phase
COD target: 2025
Total Duration
3y 5m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-31
The proposed CLPT-CLPT G20 project is a 365 MW hybrid solar and battery energy storage development in Laramie County, Wyoming. The project is located in the West region and is being proposed by CLPT, a utility also known as Black Hills Cheyenne Light Fuel and Power Transmission.
The project is currently active in the transmission interconnection queue for the utility, with an interconnection request date of July 20, 2022, and a proposed commercial operation date of December 31, 2025. The interconnection agreement (IA) for the project has been executed. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Laramie
Grid Region
Mountain West
Market
—
Developer
—
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Service Type
NRIS/ERIS
Point of Interconnection
Sweetgrass - Bluffs 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project CLPT-CLPT G20Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.