FRESNO COGENERATION EXPANSION PROJECT
91.77 MW hybrid in Fresno, CA · In queue since March 2005 · Proposed COD February 2023
91.77 MW
Capacity
2
Components
Gas + Battery
21y 4m
In Queue
IA Executed
IA Phase
COD target: 2023
Total Duration
17y 11m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2023-02-28
The Fresno Cogeneration Expansion Project is a proposed hybrid development project located in Fresno County, California, with a total capacity of 91.77 MW. The project, which combines 73.27 MW of gas generation with an 18.5 MW battery component, is interconnected to the PG&E utility via the Helm-Kerman 70 kV Line.
The project is listed in the CAISO interconnection queue as queue ID CAISO-61, with an initial queue entry date of March 30, 2005, and a proposed commercial operation date of February 28, 2023. An Interconnection Agreement (IA) for the project was executed on July 31, 2023. The project currently has an active status in the interconnection queue.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Helm-Kerman 70 kV Line
Data Source
LBNL + Live
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about FRESNO COGENERATION EXPANSION PROJECTForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.