Grapevine 1
204.57 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031
204.57 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The proposed Grapevine 1 project is a 204.57 MW solar generation project located in Nye County, Nevada. The project, developed by GLW, is currently active in the CAISO interconnection queue as entry CAISO-54945, with a queue entry date of April 17, 2023. The proposed commercial operation date is June 1, 2031.
The interconnection agreement (IA) status for Grapevine 1 is "Not Started". The point of interconnection (POI) is the VALLEY SWITCH 230 kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
VALLEY SWITCH 230 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Grapevine 1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.