Rex Solaris 2
513.544 MW hybrid in Kings, CA · In queue since April 2023 · Proposed COD March 2029
513.544 MW
Capacity
3
Components
Solar + Battery + Solar+Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-30
Rex Solaris 2 is a proposed 513.54 MW hybrid Solar+Battery project located in Kings County, California. The development project consists of 507.24 MW of solar capacity, 2.3 MW of battery capacity, and 4 MW of Solar+Battery capacity. It is interconnected to the PG&E utility network and is in the CAISO interconnection queue as entry CAISO-54709, filed on April 17, 2023.
The proposed commercial operation date for Rex Solaris 2 is March 30, 2029. As of the latest data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the GATES-MIDWAY 500kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
GATES-MIDWAY 500kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.