MATTERHORN (CAISO-2366) — Project Summary

Queue ID
CAISO-2366
Capacity
1217.79 MW
Technology
Solar+Battery
Status
active
Location
Riverside, CA
Region
CAISO
Developer
—
IA Status
Not Started

MATTERHORN

CAISO-2366BetaActiveSolarWindBatteryCAISOLBNL

1,217.79 MW hybrid in Riverside, CA · In queue since April 2023 · Proposed COD December 2029

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

1,217.79 MW

Capacity

3

Components

Solar + Wind + Battery

3y 7m

In Queue

Not Started

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 8m

Study Phase

Cluster 15

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-15

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 15, 2029
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in the CAISO queue (Cluster queue date 2023-04-17); IA not started; no public evidence of construction or permitting.
Financing
Not recorded
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/caiso-55027

Commercial operation date: Only the LBNL queue filing gives a COD (2029-12-15). None of the search results are about this project's schedule: the Enbridge Matterhorn items refer to a Texas gas pipeline, and the other hits are unrelated.

Developer: LBNL lists no developer, and no search result ties a developer to the Riverside County Matterhorn solar+storage project. The Enbridge, Matterhorn Capital Group, and Chaberton (Maryland) results are different projects or entities.

Status: LBNL reports active status with IA not started. No newer source contradicts it or shows progress.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Matterhorn project (CAISO-2366) is a proposed hybrid renewable energy development in Riverside County, California, with a total capacity of 1,217.79 MW. Although categorized as a Solar+Battery project, it combines three technologies: 404.89 MW of solar generation, 406.8 MW of wind generation, and 406.1 MW of battery energy storage. The project would connect to the Southern California Edison (SCE) system at the Devers 500 kV point of interconnection.

The project entered the California Independent System Operator (CAISO) interconnection queue on April 17, 2023, and remains active. It is being evaluated as part of CAISO's Cluster 15 study process and has requested Energy Resource Interconnection Service (ERIS). Its proposed commercial operation date is December 15, 2029. As of the latest available data, the interconnection agreement process has not started.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CA

County

Riverside

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

SCE

Entity

CAISO

Service Type

ERIS

Point of Interconnection

DEVERS 500 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar404.892 MW · 33%
Wind406.8 MW · 33%
Battery406.098 MW · 33%
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
GARNET_7_N006
POI Substation
Devers Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.