Maravillosa 2
811.87 MW hybrid in Kern, CA · In queue since April 2023 · Proposed COD June 2029
811.87 MW
Capacity
2
Components
Solar + Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 2m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-54625
- interxdata.com/projects/maravillosa-2-caiso-2361/
- interxdata.com/projects/maravillosa-solar-2-caiso-54625/
- cleanview.co/planned-battery-projects/CA/54625_storage/maravillosa-2
- cleanview.co/power-projects/planned/solar-farms/california/54625_photovoltaic/maravillosa-2
- bizapedia.com/ca/maravillosa-solar-energy-ii-llc.html
Commercial operation date: The only COD signal is the LBNL/CAISO proposed completion date of 2029-06-30. Cleanview ('expected to come online in June 2029') and interconnection.fyi ('proposed completion date is June 30, 2029') appear to mirror the queue data rather than give independent developer-backed targets.
Developer: The LBNL developer field is null and no press release or news item names a developer. A California entity called 'Maravillosa Solar Energy II LLC' exists (Bizapedia), but nothing links it to this queue entry, so it is not asserted as the developer.
Status: LBNL and the interXdata page for CAISO-2361 (last checked 2026-07-31) both show Active. A separate interXdata record, 'Maravillosa Solar 2' (54625), is marked withdrawn, but it is undated and may be a duplicate or legacy entry. I kept the LBNL status for queue ID 2361.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Maravillosa 2 is a proposed hybrid solar and battery storage development project located in Kern County, California. The project has a total combined capacity of 811.87 MW, consisting of a 407.23 MW solar photovoltaic component and a 404.64 MW battery energy storage component. No developer has been publicly identified in the available interconnection data. The project is planned to connect to the grid at the Dry Lake Switching Station at 500 kV, within the service territory of Pacific Gas and Electric Company (PG&E).
The project is listed in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2361, which it entered on April 17, 2023. It is being evaluated as part of CAISO's Cluster 15 study phase and has requested Network Resource Interconnection Service (NRIS). As of the latest available data, the project's queue status is active, and work on an interconnection agreement has not yet started. The proposed commercial operation date is June 30, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
DRY LAKE SW STA 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.