Cabrera Reliability
205.403 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD September 2028
205.403 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 5m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (4 recorded sources)
medium confidence at research time
- cleanview.co/planned-battery-projects/CA/54724_storage/cabrera-reliability
- baywa.com/binariesdownload/pdf/content/documents/baywacms-en/downloadcenter/consolidated-financial-statements/consolidated-financial-statements-2023/consolidated-financial-statements-2023/baywacms%253Adownloadpdf/BayWa+AG_KFB+2023_EN_Website.pdf
- lobbyregister.bundestag.de/media/4c/7d/643839/BayWa-r-e-AG-Konzernabschluss-2024-Veroeffentlichungsversion.pdf
- baywa.com/binaries/pdf/content/documents/baywacms/downloadcenter/quartalsberichte/halbjahresbericht-2025/halbjahresbericht-2025/baywacms%3Adownloadpdf/BayWa-Konzern_Halbjahresfinanzbericht+2025_DE_web.pdf
Commercial operation date: Only LBNL queue data provides a COD target of September 2028. Cleanview aggregator confirms this date but adds no independent verification. No press releases or developer announcements found to validate or update this timeline.
Developer: BayWa r.e. AG consolidated financial statements (2023-2025) consistently list 'Cabrera Reliability Project LLC' as a 100% owned subsidiary based in Carlsbad/Irvine, USA. The LLC is the LBNL filing entity; BayWa r.e. is the operating parent and developer.
Status: LBNL status is 'active' with IA 'Not Started'. BayWa r.e. financial disclosures through August 2025 confirm continued ownership with no indication of sale, withdrawal, or construction start.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cabrera Reliability is a proposed battery energy storage project in San Bernardino County, California, with a total capacity of 205.4 megawatts (MW). The development project consists of a single battery storage component. It would interconnect at the Lugo 500 kV substation within the service territory of Southern California Edison (SCE). No developer has been publicly identified in the available queue data.
The project is listed as active in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2353. It entered the queue on April 17, 2023, and is being studied as part of CAISO's Cluster 15. The project has requested Network Resource Interconnection Service (NRIS). As of the latest data, work on an interconnection agreement had not started. The proposed commercial operation date is September 15, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cabrera ReliabilityForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.