Crusade
1,029 MW storage in Orange, CA · In queue since April 2023 · Proposed COD December 2028
1,029 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 8m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only the LBNL queue record gives a COD (2028-12-31). The Cleanview aggregator listing repeats the December 2028 date, but it appears to be derived from the same queue data, so it is not an independent confirmation. All other search results are unrelated uses of the word 'crusade'.
Developer: The LBNL developer field is null and no search result identifies a developer or operating company for the Crusade battery project.
Status: The LBNL status is 'active' with the IA 'Not Started'. No newer source contradicts or enriches it.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Crusade is a proposed battery energy storage development project located in Orange County, California. The project has a total capacity of 1,029 MW, consisting entirely of battery storage. It is listed in the interconnection queue of the California Independent System Operator (CAISO) under queue ID CAISO-2350, within the service territory of Southern California Edison (SCE). The proposed point of interconnection is the Viejo 230 kV substation. No developer is identified in the available queue data.
The project entered the CAISO queue on April 17, 2023, and is being evaluated as part of Cluster 15. It has requested Network Resource Interconnection Service (NRIS) and has a proposed commercial operation date of December 31, 2028. As of the latest data, the project's queue status is active. Its interconnection agreement process has not yet started.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
VIEJO 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VIEJOSC_2_N004
- POI Substation
- Viejo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.