Chronos Energy Storage (CAISO-2306) — Project Summary

Queue ID
CAISO-2306
Capacity
516.8 MW
Technology
Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
—
IA Status
Not Started

Chronos Energy Storage

CAISO-2306BetaActiveOther StorageCAISOLBNL

516.8 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD November 2031

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

516.8 MW

Capacity

1

Components

Other Storage

3y 7m

In Queue

Not Started

IA Phase

COD target: 2031

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 7m

Study Phase

Cluster 15

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-11-30

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Nov 30, 2031
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in the CAISO queue, IA not started, proposed to connect at Lugo 500 kV. No public construction, permitting or offtake signals found.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/caiso-55012
  2. interxdata.com/projects/chronos-energy-storage-caiso-2306/
  3. cleanview.co/power-projects/planned/battery-storage-projects/california/55012_storage/chronos-energy-storage

Commercial operation date: Only the LBNL filing gives a COD (2031-11-30). Aggregators such as Cleanview and interconnection.fyi repeat the queue date (2031, Nov 29 2031), so they are not independent confirmation. No developer press release or news item gives a different date.

Developer: The LBNL developer field is null and no search result ties a developer to CAISO-2306. Aurora's Chronos software and Chronos Energy (powered land for AI) are unrelated entities matched on name only.

Status: LBNL lists the project as active, and interxdata (Jul 2026) and interconnection.fyi both show it active. No evidence of withdrawal or progress beyond the queue stage.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Chronos Energy Storage is a proposed battery energy storage development project located in San Bernardino County, California. The project has a total planned capacity of 516.8 MW, consisting of a single storage component classified as "Other Storage." It is situated within the service territory of Southern California Edison (SCE) and is proposed to interconnect at the Lugo 500 kV point of interconnection. No developer is identified in the available queue data.

The project is listed in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2306, which it entered on April 17, 2023. It remains in active status and is being evaluated as part of CAISO's Cluster 15 study process. The project has requested Network Resource Interconnection Service (NRIS). As of the latest available data, its interconnection agreement has not been started. The proposed commercial operation date is November 30, 2031.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CA

County

San Bernardino

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

SCE

Entity

CAISO

Service Type

NRIS

Point of Interconnection

LUGO 500 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
POI Substation
Lugo Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.