Goldlink
353.815 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2030
353.815 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Not Started
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 2m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/nevada/54768_photovoltaic/goldlink
- interconnection.fyi/projects/transmission-owner/gridliance-west
- infrasure.ai/ask/r/goldlink-queue-pipeline-1-projects-by-technology-and-status
- interconnection.fyi/projects/market/CAISO
Commercial operation date: Only LBNL-derived data exists: the queue lists a proposed COD of 2030-06-01, and aggregator sites (Cleanview, Infrasure) repeat the same date without independent confirmation. No developer press release or news item gives a different target.
Developer: LBNL developer field is null and no search result identifies a developer or parent company for Goldlink; the only hits are queue aggregators and unrelated music/hotel results.
Status: LBNL lists status as active, and interconnection.fyi and Infrasure also show Goldlink as Active. No evidence of withdrawal, IA execution, or construction.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Goldlink is a proposed solar development project in Nye County, Nevada, with a planned generating capacity of 353.81 MW. The project is listed in the interconnection queue of the California Independent System Operator (CAISO) under queue ID CAISO-2273, with GLW identified as the interconnecting utility. No developer has been publicly identified in the available queue data.
The project entered the CAISO queue on April 17, 2023, and is being evaluated as part of the Cluster 15 study phase. It holds an active status and has requested Energy Resource Interconnection Service (ERIS). The proposed point of interconnection is the Lathrop 230 kV substation, which is designated as a future facility. As of the latest data, negotiation of an interconnection agreement has not started. The project's proposed commercial operation date is June 1, 2030.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
ERIS
Point of Interconnection
LATHROP 230 kV (FUTURE)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Nevada
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Goldlink in ISO New England queue pipeline — 1 projects by technology and status
Data-driven briefing on Goldlink — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.