Sienna 3
576 MW hybrid in San Bernardino, CA · In queue since April 2023 · Proposed COD December 2031
576 MW
Capacity
2
Components
Solar + Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 8m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
Commercial operation date: Only the LBNL snapshot gives a COD (proposed 2031-12-31). The search results contain no press release, news item or developer announcement with a different target date.
Developer: LBNL lists no developer, and none of the search results name an operating company or parent for Sienna 3. Nearly all the results are unrelated Toyota Sienna or consumer content.
Status: LBNL reports active status, and interconnection.fyi lists the project as Active in CAISO. Nothing in the results contradicts this.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Sienna 3 (queue ID CAISO-2268) is a proposed hybrid solar and battery storage development project located in San Bernardino County, California. The project has a total capacity of 576 MW, consisting of a 288 MW solar photovoltaic component paired with a 288 MW battery energy storage component. No developer is identified in the available queue data. The project is planned to interconnect at the Calcite 230 kV point of interconnection within the service territory of Southern California Edison (SCE).
The project entered the California Independent System Operator (CAISO) interconnection queue on April 17, 2023, and is currently listed with an active status. It is being evaluated as part of CAISO's Cluster 15 study phase and has requested Energy Resource Interconnection Service (ERIS). As of the latest data, the interconnection agreement (IA) process has not started. The project's proposed commercial operation date is December 31, 2031.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
CALCITE 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.