Muon
2,339.008 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD September 2028
2,339.008 MW
Capacity
2
Components
Solar + Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 5m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/arkansas/54634_storage/muon
- facebook.com/unboxfactory/posts/california-has-become-one-of-the-worlds-most-important-examples-of-how-large-sca/1153793366971712/
Commercial operation date: LBNL proposed COD is 2028-09-30. The Cleanview tracker listing says 'Expected online 2028', which is consistent but probably derives from the same queue data. No developer press release or news item gives an independent date.
Developer: The LBNL developer field is null and no search result names a developer for this Fresno County project. Every other 'Muon' hit is unrelated (Muon Space satellites, muon physics).
Status: LBNL shows active status with IA 'Not Started'. Cleanview lists it as planned, and no evidence of construction, withdrawal or suspension was found.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Muon is a proposed hybrid solar and battery storage development project located in Fresno County, California. The project has a total capacity of 2,339.01 MW, consisting of a 1,169.5 MW solar photovoltaic component paired with a 1,169.5 MW battery energy storage component. It is planned to interconnect within the service territory of Pacific Gas and Electric Company (PG&E) at the Harlan Switching Station 500 kV point of interconnection.
The project is listed in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2266, with a queue entry date of April 17, 2023. It is being studied as part of CAISO's Cluster 15 and has requested Network Resource Interconnection Service (NRIS). As of the most recent data, the project's queue status is active, though its interconnection agreement (IA) process has not yet started. The proposed commercial operation date is September 30, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
HARLAN SW STA 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.