Cassia
102.15 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD March 2031
102.15 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 11m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/california/54721_storage/cassia
- caiso.com/documents/cluster-15-interconnection-requests.xlsx
Commercial operation date: Only source is LBNL queue filing showing March 2031 COD. Cleanview aggregator mirrors this date but provides no independent verification. No developer announcements or press releases found.
Developer: LBNL filing shows no developer. No press releases, corporate announcements, or ownership records found in search results. Project appears to be early-stage with no public developer identity.
Status: LBNL shows 'active' status with IA 'Not Started'. No evidence of permitting, financing, or development activity in public records. Appears to be placeholder queue position.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cassia is a proposed battery energy storage project located in San Joaquin County, California. The development project has a total capacity of 102.15 MW, consisting entirely of a single battery storage component. No developer is identified in the available data. The project is planned to connect to the grid at the Lammers 115 kV point of interconnection, within the service territory of Pacific Gas and Electric Company (PG&E).
The project is listed in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2261, with a queue entry date of April 17, 2023. It is being evaluated as part of CAISO's Cluster 15 study phase and has requested Network Resource Interconnection Service (NRIS). As of the latest data, the project's queue status is active, though its interconnection agreement process has not yet started. The proposed commercial operation date is March 31, 2031.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
LAMMERS 115 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAMMERS_1_N001
- POI Substation
- Lammers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about CassiaForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.