Sunglow (CAISO-2260) — Project Summary

Queue ID
CAISO-2260
Capacity
744.33 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
—
IA Status
Not Started

Sunglow

CAISO-2260BetaActiveSolarBatteryCAISOLBNL

744.33 MW hybrid in Kings, CA · In queue since April 2023 · Proposed COD October 2030

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

744.33 MW

Capacity

2

Components

Solar + Battery

3y 7m

In Queue

Not Started

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 6m

Study Phase

Cluster 15

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-10-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 1, 2030
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in CAISO queue (Cluster 2260, Kings County); IA not started; no public construction, permitting or financing news found.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/california/54905_storage/sunglow
  2. interconnection.fyi/project/caiso-54905
  3. interconnection.fyi/projects/market/CAISO

Commercial operation date: Only LBNL gives a specific date (2030-10-01). Cleanview's 'Expected online 2030' agrees with it but appears to be derived from the same queue data, so it is not an independent post-LBNL signal.

Developer: LBNL developer field is null and no search result names a developer for the Kings County Sunglow project. The Sunglow switchyard in the NADBank document belongs to a Texas project (Fort Duncan) and is unrelated.

Status: LBNL lists the project as active and interconnection.fyi also shows it as Active. No source indicates withdrawal or construction.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Sunglow (CAISO queue ID CAISO-2260) is a proposed hybrid solar and battery storage development project in Kings County, California. The project has a total capacity of 744.33 MW, made up of a 372.17 MW solar photovoltaic component and a 372.17 MW battery energy storage component. It is located within the service territory of Pacific Gas and Electric Company (PG&E) and would interconnect to the grid at the Manning 500 kV point of interconnection.

The project entered the California Independent System Operator (CAISO) interconnection queue on April 17, 2023, and is being studied as part of Cluster 15. It has requested Network Resource Interconnection Service (NRIS). As of the latest available data, the project's queue status is active, and its interconnection agreement process has not yet started. The proposed commercial operation date is October 1, 2030.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CA

County

Kings

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

PG&E

Entity

CAISO

Service Type

NRIS

Point of Interconnection

MANNING 500 kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar372.165 MW · 50%
Battery372.165 MW · 50%
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.