Solstice C
408.16 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
408.16 MW
Capacity
2
Components
Solar + Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 1m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
Commercial operation date: Only the LBNL snapshot gives a COD (proposed 2031-05-01). The search results contain no developer press release, news item or financing announcement that confirms or contradicts it.
Developer: The LBNL developer field is null and no search result names a developer or parent company. The only relevant hits are interconnection.fyi queue listings, which do not name one.
Status: LBNL lists status as active with IA 'Not Started'. The interconnection.fyi listing also shows Active, which is consistent but not independent of the queue data.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Solstice C (queue ID CAISO-2253) is a proposed hybrid solar and battery storage development project in Fresno County, California. It has a total capacity of 408.16 MW, made up of a 204.53 MW solar photovoltaic component and a 203.63 MW battery energy storage component. The project would interconnect at the Manning 500 kV point of interconnection within the Pacific Gas and Electric Company (PG&E) service territory. No developer is identified in the available data.
The project is listed as active in the California Independent System Operator (CAISO) interconnection queue, which it entered on April 17, 2023. It is being evaluated as part of CAISO's Cluster 15 study process and has requested Network Resource Interconnection Service (NRIS). The proposed commercial operation date is May 1, 2031. As of the latest available data, work on an interconnection agreement had not started.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PG&E
Entity
CAISO
Service Type
NRIS
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.