Fika
258.47 MW storage in Merced, CA · In queue since April 2023 · Proposed COD June 2029
258.47 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 2m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection request submitted to CAISO as part of Cluster 15
caiso.comResearch sources and reasoning (5 recorded sources)
low confidence at research time
- cleanview.co/planned-battery-projects/CA/54862_storage/fika
- caiso.com/documents/cluster-15-interconnection-requests.xlsx
- renewablesinfo.org/project/caiso-54862-fika-solar
- cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/2024-2026-irp-cycle-events-and-materials/assumptions-for-the-2025-2026-tpp/mappingcifrom_cluster15_apps_09-25-24.xlsx
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
Commercial operation date: LBNL queue filing shows proposed COD of 2029-06-30. Cleanview aggregator site confirms June 2029 expected online date. No independent news sources or press releases found to validate or contradict this date.
Developer: LBNL filing shows null developer. No press releases, corporate announcements, or news coverage found identifying the project sponsor. CAISO Cluster 15 spreadsheet and CPUC commercial interest analysis list project name only without developer attribution.
Status: LBNL shows active queue status with IA not started. LBNL hybrid plant tracking confirms 'active' status with interconnection 'In Progress (unknown phase)'. No news of construction, financing, or development milestones.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Fika is a proposed battery energy storage development project located in Merced County, California. The project has a total capacity of 258.47 MW, consisting entirely of a single battery storage component. It is planned to interconnect at the Quinto Switching Station at 230 kV, within the service territory of Pacific Gas and Electric Company (PG&E). No developer is identified in the available data.
The project is listed as active in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2216. It entered the queue on April 17, 2023, and is being studied as part of CAISO's Cluster 15. The project has requested Network Resource Interconnection Service (NRIS). As of the latest available data, work on its interconnection agreement has not started. The proposed commercial operation date is June 30, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
QUINTO SW STA 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.