Octans
206.452 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD December 2031
206.452 MW
Capacity
2
Components
Solar + Battery
3y 7m
In Queue
Not Started
IA Phase
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 8m
Study Phase
Cluster 15
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
CAISO Cluster 15 queue entry with December 2031 proposed COD
caiso.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- caiso.com/documents/cluster-15-interconnection-requests.xlsx
- cleanview.co/power-projects/planned/battery-storage-projects/california/54637_storage/octans
- interconnection.fyi/project/caiso-54637
Commercial operation date: LBNL queue snapshot shows December 2031 COD. Multiple aggregator sites (Cleanview, interconnection.fyi) confirm this same date. No press releases or developer announcements found to contradict or update this timeline.
Developer: No developer identified in LBNL data. Search results yielded no press releases, corporate announcements, or ownership information for this CAISO project. Note: Results show an unrelated ERCOT project named 'Octans' in Texas owned by ENGIE, but this is a different facility.
Status: LBNL shows 'active' status with IA 'Not Started'. CAISO Cluster 15 documentation confirms project is in queue. No evidence of construction activity, financing, or permitting progress.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Octans (CAISO-2214) is a proposed hybrid solar and battery storage development project located in Fresno County, California. The project has a total capacity of 206.45 MW, consisting of a 103.23 MW solar photovoltaic component paired with a 103.23 MW battery energy storage component. It is planned to interconnect at the Oro Loma 70 kV point of interconnection within the service territory of Pacific Gas and Electric Company (PG&E).
The project entered the California Independent System Operator (CAISO) interconnection queue on April 17, 2023, and is currently listed with an active status. It is being evaluated as part of CAISO's Cluster 15 study process and has requested Energy Resource Interconnection Service (ERIS). As of the latest available data, an interconnection agreement has not yet been started. The project's proposed commercial operation date is December 1, 2031.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
ORO LOMA 70 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Octans
Data-driven briefing on Octans — fleet, generation, financial, and news signals.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.