DESERT JEWEL STORAGE
206.31 MW storage in San Diego, CA · In queue since April 2021 · Proposed COD August 2029
206.31 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed May 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 1m
IA → COD
4y 3m
Total Duration
4y 1m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2029-08-05
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (4 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.xlsx
- interconnection.fyi/project/caiso-2173
- cleanview.co/power-projects/planned/battery-storage-projects/california/2173_storage/desert-jewel-storage
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
Commercial operation date: LBNL queue shows proposed COD of 2029-08-05. No press releases, financing announcements, or developer statements found in search results to validate or contradict this date. Project appears to be in early development with IA recently executed (May 2025).
Developer: LBNL snapshot lists developer as null. Search results contain no press releases, corporate announcements, or news articles specifically identifying the developer or owner of Desert Jewel Storage. General San Diego battery storage articles mention other projects but not this one.
Status: LBNL shows 'active' status with IA executed on 2025-05-15, indicating the project has secured interconnection rights and is proceeding through development. No withdrawal or cancellation signals found in research.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Desert Jewel Storage project is a proposed 206.31 MW battery energy storage system located in San Diego County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2173, with a queue entry date of April 15, 2021. The proposed commercial operation date is August 5, 2029.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Boulevard East Substation at 138 kV. The project is within the San Diego Gas & Electric (SDGE) service area. The Desert Jewel Storage project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Boulevard East Substation 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about DESERT JEWEL STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.