SUNBAKED SOLAR
1,023.64 MW hybrid in Inyo, CA · In queue since April 2021 · Proposed COD February 2029
1,023.64 MW
Capacity
2
Components
Solar + Battery
5y 3m
In Queue
IA Executed
IA Phase
Signed Dec 2024
Queue → IA
3y 8m
IA → COD
4y 2m
Total Duration
3y 8m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-02-26
The proposed SUNBAKED SOLAR project is a 1023.64 MW hybrid solar and battery energy storage development in Inyo County, California. The project consists of a 508.56 MW solar array coupled with a 515.08 MW battery energy storage system. It is located within the CAISO region and is interconnected to the Trout Canyon Substation at 230 kV.
SUNBAKED SOLAR entered the CAISO interconnection queue as queue ID CAISO-2149 on April 15, 2021, with a proposed commercial operation date of February 26, 2029. The project's interconnection agreement has been executed. The transmission provider is GLW.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Inyo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CANYONP4_7_GN001
- POI Substation
- Canyon
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.