MOSEY
1,080.863 MW hybrid in Clark, NV · In queue since April 2021 · Proposed COD June 2029
1,080.863 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Dec 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 8m
IA → COD
4y 6m
Total Duration
3y 8m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 18–30 months
Proposed COD: 2029-06-27
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- pvtimes.com/news/mosey-solar-enters-public-scoping-period-189292/
- nyecountynv.gov/1271/BLM-Notice-of-Intent-for-Mosey-Solar-Pro
- federalregister.gov/documents/2026/07/29/2026-15270/notice-of-intent-to-prepare-a-resource-management-plan-amendment-and-environmental-impact-statement
- eplanning.blm.gov/Project-Home/?id=421fb851-8a87-f111-ab0f-001dd802f839
- fox5vegas.com/2026/07/31/federal-agency-approves-500-megawatt-mosey-solar-project-near-pahrump/
Commercial operation date: No search result gives a developer COD target. The only date is the LBNL proposed COD of 2029-06-27. The project only entered BLM EIS scoping in July 2026, so that date looks aggressive but cannot be contradicted.
Developer: The LBNL developer field is null. Pahrump Valley Times and the Nye County BLM notice name Renew Development HoldCo, LLC as the BLM applicant for the Mosey Solar Project. That is the only developer identification, so there is nothing to compare against LBNL.
Status: LBNL shows the queue entry as active with an executed IA, and the BLM NEPA register and Federal Register notice confirm the project is still moving through permitting. No source reports withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The MOSEY project is a proposed 1080.86 MW hybrid solar and battery energy storage project located in Clark County, Nevada. The development project consists of a 543.86 MW solar array coupled with a 537.01 MW battery energy storage system.
The project is listed in the CAISO interconnection queue as entry CAISO-2148, with a queue entry date of April 15, 2021. The proposed commercial operation date is June 27, 2029, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Trout Canyon Substation at 230 kV. The transmission provider is GLW.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.