LOS NIETOS
102.26 MW storage in Orange, CA · In queue since April 2021 · Proposed COD March 2032
102.26 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Aug 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 4m
IA → COD
6y 7m
Total Duration
4y 4m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2032-03-27
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Large Generator Interconnection Agreement executed with CAISO
caiso.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- caiso.com/documents/list-of-large-generator-interconnection-agreements-and-small-generator-interconnection-agreements.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/california/2129_storage/los-nietos
- interconnection.fyi/project/caiso-2129
Commercial operation date: Only LBNL queue data provides a COD target of April 2031. No news sources or press releases found to confirm or update this date.
Developer: CAISO LGIA list identifies 'RE Los Nietos LLC' as the project entity. No news coverage found identifying a parent company or operating entity behind this LLC.
Status: LBNL data shows IA executed on 2025-08-04. No news coverage found to indicate construction start or other status changes.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Los Nietos project is a proposed 102.26 MW battery storage project located in Orange County, California. The project is interconnected to Southern California Edison (SCE) and is in the California Independent System Operator (CAISO) queue as entry CAISO-2129, with a queue entry date of April 15, 2021. The proposed commercial operation date is April 26, 2031.
The project's interconnection status is currently in the System Impact Study phase. Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Johanna Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JOHANNA_2_N007
- POI Substation
- Johanna Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.