GABRIEL STORAGE
405.751 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2033
405.751 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 2m
IA → COD
7y 11m
Total Duration
4y 2m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2033-05-15
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/california/69509_1/gabriel
- energy-storage.news/aypa-power-secures-california-ra-agreements-with-investor-owned-utility-totalling-2gwh/
- irwindaleca.gov/806/Gabriel-Battery-Energy-Storage-System-BE
- infrasure.ai/plant/69509-gabriel
- interxdata.com/projects/gabriel-storage-caiso-public-queue-2113/
Commercial operation date: Cleanview's project-level record (Gabriel, 400 MW, Los Angeles) says 'Expected online 2027'. The 2033 LBNL date looks like a queue placeholder, since the IA was executed in June 2025 and Aypa has signed RA agreements for the Gabriel project. Only one source gives 2027 and the link between records is inferred, so this is a low-confidence correction.
Developer: LBNL lists no developer. Energy-Storage.News shows Aypa Power's 'Gabriel Battery Storage project' presented to Peninsula Clean Energy, and InfraSure lists the 400 MW Gabriel plant under the project entity 'San Gabriel Project LLC'. That LLC is not the LBNL filing entity, so developer_legal_entity stays null.
Status: LBNL shows status 'active' with an executed IA (2025-06-10), and the Irwindale city project page confirms a live local entitlement process. No source indicates construction start, withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Gabriel Storage project is a proposed 405.75 MW battery energy storage system located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2113, with a queue entry date of April 15, 2021. The proposed commercial operation date is May 15, 2033. The project's interconnection status is currently in the System Impact Study phase.
The project, which is interconnected with Southern California Edison (SCE), has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Rio Hondo Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RIOHONDO_6_N001
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
GABRIEL STORAGE
Data-driven briefing on GABRIEL STORAGE — fleet, generation, financial, and news signals.
Gabriel
Data-driven briefing on Gabriel — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.