CADY SOLAR
625.92 MW hybrid in San Bernardino, CA · In queue since April 2021 · Proposed COD February 2031
625.92 MW
Capacity
2
Components
Solar + Battery
5y 3m
In Queue
IA Executed
IA Phase
Signed Jul 2025
Queue → IA
4y 3m
IA → COD
5y 7m
Total Duration
4y 3m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2031-02-26
The CADY SOLAR project is a proposed 625.92 MW hybrid solar and battery energy storage project located in San Bernardino County, California. The development project consists of 312.96 MW of solar photovoltaic generation and 312.96 MW of battery energy storage. Interconnection is being sought through the CAISO queue, with queue ID CAISO-2103, and a queue entry date of April 15, 2021. The current interconnection status is System Impact Study, and the proposed commercial operation date is February 26, 2031.
The project is interconnected to Southern California Edison (SCE) at the Pisgah Substation 230 kV. The CADY SOLAR project has been the subject of recent news coverage, with three articles categorized as industry news and grid-related.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Pisgah Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Pisgah Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.