MINERAL KING SOLAR (CAISO-2081) — Project Summary

Queue ID
CAISO-2081
Capacity
429.5107 MW
Technology
Solar+Battery
Status
active
Location
Tulare, CA
Region
CAISO
Developer
—
IA Status
System Impact Study

MINERAL KING SOLAR

CAISO-2081BetaActiveSolarBatteryCAISOLBNL + Live

429.511 MW hybrid in Tulare, CA · In queue since April 2021 · Proposed COD September 2029

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

429.511 MW

Capacity

2

Components

Solar + Battery

5y 7m

In Queue

System Impact Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 5m

Study Phase

C14

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

Active sheet; C14

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-26

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 26, 2029
From queue filing
Developer in saved assessment
—
Status at research time
Active
Active in CAISO queue (Cluster 14), at System Impact Study stage; no IA executed and no public construction or financing signals.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/caiso-2081
  2. caiso.com/documents/publicqueuereport.pdf
  3. interconnection.fyi/projects/market/CAISO

Commercial operation date: Only the LBNL/CAISO queue date (2029-09-26) exists; the interconnection.fyi page repeats the same proposed completion date as a queue mirror, not as an independent developer-backed signal. No news or press release gives a different target.

Developer: LBNL developer field is null and no search result names a developer, parent, or operating company for Mineral King Solar.

Status: LBNL status is active and the CAISO public queue report and queue aggregators list the project as ACTIVE. No evidence of withdrawal or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed MINERAL KING SOLAR project is a 429.51 MW hybrid solar and battery energy storage system located in Tulare County, California. The project, which consists of 215.41 MW of solar generation and 214.1 MW of battery storage, is interconnected to Southern California Edison (SCE) via the Rector Substation 220 kV.

The project is listed in the CAISO interconnection queue under queue ID CAISO-2081, with an entry date of April 15, 2021. Its proposed commercial operation date is September 26, 2029. The project's interconnection status is currently in the System Impact Study phase.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • CAISO queue source as of: Oct 24, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CA

County

Tulare

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

SCE

Entity

CAISO

Service Type

NRIS

Point of Interconnection

Rector Substation 220 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar215.412 MW · 50%
Battery214.098 MW · 50%
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
RECTOR_6_N009
POI Substation
Rector Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.