DRIFTER ENERGY STORAGE
504.8 MW storage in Ventura, CA · In queue since April 2021 · Proposed COD March 2033
504.8 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Jul 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 3m
IA → COD
7y 8m
Total Duration
4y 3m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2033-03-26
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-2066
- interxdata.com/projects/drifter-energy-storage-caiso-public-queue-2066/
Commercial operation date: The only COD signal is the LBNL/CAISO proposed completion date of March 26, 2033. Aggregator pages (interconnection.fyi, Cleanview) repeat that date and are not independent. No developer press release or news article gives a different target.
Developer: The LBNL developer field is null. The news-extracted 'Prologis' comes from a Moorpark city-council article on indoor battery bans, and nothing in it names Drifter or CAISO-2066. The Saticoy/Oxnard 2021 article describes a different, already-operating facility. The Moorpark Substation POI is only circumstantial, so I did not attribute a developer.
Status: LBNL shows status active and IA Executed, and the aggregator pages agree it is active. No source indicates withdrawal, suspension or construction. The news-extracted 'operational' status belongs to an unrelated 2021 Oxnard article.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The DRIFTER ENERGY STORAGE project is a proposed 504.8 MW battery storage project located in Ventura County, California. The project is interconnected to the CAISO grid via the Moorpark Substation at 230 kV and is in the CAISO interconnection queue as entry CAISO-2066, with a queue entry date of April 15, 2021. The proposed commercial operation date is March 26, 2033, and the project's interconnection status is currently in the System Impact Study phase.
The DRIFTER ENERGY STORAGE project is proposed by an unknown developer and connects to Southern California Edison (SCE). The project has been the subject of recent news coverage, with four articles categorized as industry, regulatory, and grid-related.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Ventura
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Moorpark Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MOORPARK_6_N005
- POI Substation
- Moorpark Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesBattery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.