SAGEBRUSH ENERGY STORAGE
528 MW storage in Kern, CA · In queue since April 2021 · Proposed COD February 2033
528 MW
Capacity
1
Components
Battery
5y 7m
In Queue
System Impact Study
IA Phase
COD target: 2033
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11y 10m
Study Phase
C14
Interconnection request submitted to ISO/RTO
Active sheet; IA Executed; C14
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-02-26
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/projects/market/CAISO
- interconnection.fyi/projects/state/CA/kern-county
- gridvisionai.com/retrospectives/caiso-vincent-substation-230-kv
Commercial operation date: Only the LBNL snapshot gives a COD (proposed_cod 2033-02-26). No news or press-release source gives a developer-backed target. The 80MW/320MWh 'Sagebrush Energy Storage' in Mojave and the BuildZoom permit are likely a different, smaller project, so I did not use them to override the date.
Developer: LBNL lists no developer, and none of the search results ties an operating company to CAISO-2060. The Terra-Gen settlement article does not mention this project in its snippet, so I did not link them.
Status: LBNL status is 'active', and interconnection.fyi and gridvisionai list the project as still in queue or active. Nothing indicates withdrawal or construction.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SAGEBRUSH ENERGY STORAGE project is a proposed 528 MW battery storage project located in Kern County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2060, with a queue entry date of April 15, 2021. The proposed commercial operation date is February 26, 2033. The project's interconnection status is currently in the System Impact Study phase and it would connect to the Vincent Substation at 230 kV.
The SAGEBRUSH ENERGY STORAGE project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Vincent Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VINCENT_2_N101
- POI Substation
- Vincent Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
SAGEBRUSH ENERGY STORAGE
Data-driven briefing on SAGEBRUSH ENERGY STORAGE — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.