SANDRIFT STORAGE 1
254.77 MW storage in Riverside, CA · In queue since April 2021 · Proposed COD December 2030
254.77 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Sep 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 5m
IA → COD
5y 3m
Total Duration
4y 5m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2030-12-26
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (4 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.xlsx
- wecc.org/sites/default/files/documents/progress_report/2026/SCE%202026%20APR.pdf
- docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M534/K048/534048570.PDF
- interconnection.fyi/project/caiso-2039
Commercial operation date: LBNL queue shows December 26, 2030 COD, confirmed in CAISO public queue report and WECC progress report. No developer announcements or press releases found to validate or contradict this date.
Developer: No developer identified in LBNL data. Search results include only queue aggregator sites and regulatory filings with no developer attribution. 2018 Desert Sun article mentions large battery projects in California desert but does not name Sandrift or its developer.
Status: LBNL shows 'Active' status with IA executed on September 27, 2025. CAISO public queue reports confirm active status. No construction announcements or withdrawal notices found.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SANDRIFT STORAGE 1 project is a proposed battery storage project located in Riverside County, California, with a total capacity of 254.77 MW. The project is in the CAISO interconnection queue (queue ID CAISO-2039) as of April 15, 2021, and has a proposed commercial operation date of December 26, 2030. The project's interconnection point is the Red Bluff Substation at 230 kV.
The SANDRIFT STORAGE 1 project's interconnection status is currently in the System Impact Study phase. The project is interconnected with Southern California Edison (SCE) within the CAISO region. Recent news coverage has discussed the project's progress and potential impact on the grid.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Red Bluff Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OBERON_7_N122
- POI Substation
- Red Bluff Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.