SERENA STORAGE
114.264 MW storage in Kern, CA · In queue since April 2021 · Proposed COD February 2032
114.264 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Sep 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 5m
IA → COD
6y 5m
Total Duration
4y 5m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2032-02-16
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with CAISO
caiso.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.xlsx
- cleanview.co/power-projects/planned/battery-storage-projects/california/2001_storage/serena-storage
- renewablesinfo.org/project/caiso-2001-serena-storage
Commercial operation date: LBNL queue shows September 2029 COD. Cleanview aggregator sites confirm this date but cite LBNL as source. No independent developer announcements or press releases found to validate or update this target.
Developer: LBNL filing shows null developer. Search results include only aggregator sites (Cleanview, renewablesinfo.org) that mirror LBNL data with no developer attribution. No press releases, corporate announcements, or ownership records found.
Status: LBNL shows 'Active' with IA executed 2025-09-29. No news coverage of groundbreaking, financing, or development activity. Project appears to be in post-IA pre-construction phase.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SERENA STORAGE project is a proposed 114.26 MW battery energy storage system located in Kern County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2001, with a queue entry date of April 15, 2021. The proposed commercial operation date is September 18, 2029. The project's interconnection status is currently in the System Impact Study phase.
The project, which is being developed within the Pacific Gas and Electric (PGAE) service area, has been mentioned in recent news coverage related to regulatory and development matters. The point of interconnection is the Kern PP 230 kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Kern PP 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about SERENA STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.