100.9 MW storage in Kern, CA · In queue since April 2021 · Proposed COD February 2032
100.9 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-02-16
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The EIGER ENERGY STORAGE project is a proposed 100.9 MW battery storage project located in Kern County, California. Interconnection is requested through the CAISO queue, with queue ID CAISO-1994. The project entered the queue on April 15, 2021, and has a proposed commercial operation date of February 16, 2032. The project's interconnection status is currently in the System Impact Study phase, and it is requesting interconnection to the PG&E grid at the Lamont 115 kV point of interconnection.
The development project consists solely of battery storage, with a total capacity of 100.9 MW. It is currently listed as an active project within the CAISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lamont 115 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about EIGER ENERGY STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.