LOCK STORAGE (CAISO-1962) — Project Summary

Queue ID
CAISO-1962
Capacity
508 MW
Technology
Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
—
IA Status
IA Executed

LOCK STORAGE

CAISO-1962BetaActiveBatteryCAISOLBNL + Live

508 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD December 2027

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

508 MW

Capacity

1

Components

Battery

5y 7m

In Queue

IA Executed

IA Phase

Signed Apr 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4 years

IA → COD

2y 8m

Total Duration

4 years

Study Phase

C14

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementApr 30, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Active sheet; IA Executed; C14

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-12-15

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 15, 2027
From queue filing
Developer in saved assessment
—
Status at research time
IA Executed
Active in the CAISO queue (position 1962, Fresno County, 508 MW battery) with an IA executed 2025-04-30. No news confirms construction or financing.
Financing
Not recorded

Milestones in this assessment

IA executedApr 30, 2025Latest in this assessment

LBNL records the interconnection agreement as executed on 2025-04-30. The CAISO queue report lists the project as ACTIVE but does not itself show the IA date.

caiso.com
Research sources and reasoning (2 recorded sources)

low confidence at research time

  1. caiso.com/documents/publicqueuereport.pdf
  2. gridstatus.io/interconnection-queue/ix_caiso_6abc5680

Commercial operation date: Only the LBNL snapshot gives a COD (proposed 2027-12-15). The search results are almost all irrelevant retail or self-storage hits, and the GridStatus and CAISO queue pages confirm the project exists but give no newer date.

Developer: LBNL lists no developer, and no search result names a developer or parent company for Lock Storage. The GridStatus and CAISO pages list only the project name, MW and queue position.

Status: LBNL shows status active and IA Executed with an IA date of 2025-04-30. The CAISO public queue report lists the project as ACTIVE, and nothing contradicts this.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The LOCK STORAGE project is a proposed 508 MW battery storage project located in Fresno County, California. Interconnecting to the PG&E utility, the project is in the CAISO interconnection queue as entry CAISO-1962, with a queue entry date of April 15, 2021. The proposed commercial operation date is December 15, 2027. The project's interconnection status is currently in the System Impact Study phase.

The LOCK STORAGE project has been the subject of recent news coverage, with three articles categorized as regulatory and industry news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • CAISO queue source as of: Oct 24, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

CA

County

Fresno

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

PGAE

Entity

CAISO

Service Type

NRIS

Point of Interconnection

Gates 500 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
FIFTHS_7_N003
POI Substation
Gates Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.