AUSTRALIS
614 MW hybrid in Merced, CA · In queue since April 2021 · Proposed COD April 2031
614 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 10m
IA → COD
6y 2m
Total Duration
3y 10m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 18–30 months
Proposed COD: 2031-04-18
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
LBNL lists the interconnection agreement as executed on 2025-02-23. The CAISO queue report confirms the project is active in Cluster 14.
caiso.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/california/1952_storage/australis
- interconnection.fyi/project/caiso-1952
- gridvisionai.com/retrospectives/caiso-los-banos-230-kv
Commercial operation date: Only the LBNL proposed COD (2031-04-18) exists. Cleanview's 'expected to come online in April 2031' matches it but appears to be derived from the same queue data, so it is not an independent post-LBNL signal.
Developer: LBNL developer field is null and no search result names a developer or parent company for AUSTRALIS. The results are queue listings and unrelated Australian or oil-and-gas 'Australis' entities.
Status: LBNL shows active with an executed IA. The CAISO public queue report and the GridVision, interconnection.fyi and Cleanview listings all still show the project in queue. None reports construction.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The AUSTRALIS project is a proposed 614 MW hybrid solar and battery energy storage project located in Merced County, California. The development project consists of 307 MW of solar photovoltaic generation paired with 307 MW of battery energy storage. The project is interconnected within the CAISO region and is in the Pacific Gas & Electric (PGAE) service area.
The project, identified as CAISO-1952 in the CAISO interconnection queue, entered the queue on April 15, 2021, with a proposed commercial operation date of April 18, 2031. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Los Banos 230 kV substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Los Banos 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SNTANLA_6_N001
- POI Substation
- Los Banos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.