713.184 MW hybrid in San Joaquin, CA · In queue since April 2021 · Proposed COD December 2030
713.184 MW
Capacity
2
Components
Solar + Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Dec 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 8m
IA → COD
6 years
Total Duration
3y 8m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 18–30 months
Proposed COD: 2030-12-16
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed per LBNL queue data; the interconnection.fyi page lists the project as active in CAISO.
interconnection.fyiResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: No live search result refers to this San Joaquin County solar+storage project. The hits cover Presidio, TX, Presidio Park in San Diego, the Presidio Trust in San Francisco, and an ASX oil and gas company. The only COD signal is the LBNL proposed_cod of 2030-12-16.
Developer: The LBNL developer field is null and no search result names a developer for CAISO-1887. The unrelated Presidio hits (Presidio Partners, Helios Energy, Presidio Trust) cannot be tied to this project.
Status: LBNL lists status as active with an executed IA. The interconnection.fyi listing also shows the project as active in CAISO, and nothing in the search results contradicts this.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The PRESIDIO project is a proposed 713.18 MW hybrid solar and battery energy storage project located in San Joaquin County, California. The development project consists of 356.59 MW of solar photovoltaic generation paired with 356.59 MW of battery energy storage. The project is interconnected to the PG&E utility network within the CAISO region, and it is listed in the CAISO interconnection queue as queue ID CAISO-1887.
The PRESIDIO project entered the CAISO queue on April 15, 2021, and has a proposed commercial operation date of December 16, 2030. The project's interconnection agreement has been executed. The point of interconnection is the Rancho Seco-Bellota #1 230 kV Line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Rancho Seco-Bellota #1 230 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.