DELILAH ENERGY STORAGE
504 MW storage in Contra Costa, CA · In queue since April 2021 · Proposed COD July 2032
504 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Sep 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 5m
IA → COD
6y 10m
Total Duration
4y 5m
Study Phase
C14
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C14
Project under construction
Typical: 6–18 months
Proposed COD: 2032-07-19
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- caiso.com/documents/publicqueuereport.pdf
- interconnection.fyi/projects/market/CAISO
- infrasure.ai/ask/r/delilah-energy-storage-queue-pipeline-1-projects-by-technology-and-status
- prnewswire.com/news-releases/invenergy-to-provide-over-760mw-in-renewable-energy-supporting-metas-energy-needs-in-line-with-its-clean-and-renewable-energy-goals-302323252.html
Commercial operation date: Only the LBNL/CAISO queue date (proposed COD 2032-07-19) exists. The infrasure.ai page repeats the same queue data ('Proposed COD is 2032-07') and is not an independent signal. No developer press release or news item gives a different target.
Developer: LBNL lists no developer. The news-extracted 'Invenergy' attribution comes from a Meta PPA release and 'Delilah I' coverage, which concern a 300 MW Texas solar farm. That looks like a name collision with the CAISO Delilah Energy Storage project in Contra Costa County, and nothing links Invenergy to the California project, so I did not accept it.
Status: LBNL and the CAISO public queue report both show ACTIVE, and the snapshot shows an executed IA. The searches found no withdrawal, construction or suspension news.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Delilah Energy Storage project is a proposed 504 MW battery storage project located in Contra Costa County, California. The project is interconnected within the CAISO region, with Pacific Gas & Electric (PGAE) as the utility. It entered the CAISO interconnection queue as queue ID CAISO-1875 on April 15, 2021. The proposed commercial operation date is July 19, 2032, and its current interconnection status is System Impact Study.
The Delilah Energy Storage project has been the subject of recent news coverage, with 76 articles published. A majority of the articles (69) are categorized as "deals," with the remainder focusing on "industry" and "regulatory" topics.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Contra Costa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Pittsburg-Tesla #1 230 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBattery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
DELILAH ENERGY STORAGE Battery Storage in ISO New England growth signals — PPAs, construction, new projects
Data-driven briefing on DELILAH ENERGY STORAGE — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.