SANBORN 5 HYBRID
560.33 MW generation in Kern, CA · In queue since April 2020 · Proposed COD April 2028
560.33 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Phase
Signed Sep 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 5m
IA → COD
4y 7m
Total Duration
3y 5m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/california/1791_photovoltaic/sanborn-5-hybrid
- cleanview.co/power-projects/planned/battery-storage-projects/california/1791_storage/sanborn-5-hybrid
- energy-storage.news/officials-in-kern-county-california-begin-permitting-process-for-terra-gens-8gwh-ldes-bess/
- interconnection.fyi/project/caiso-1791
Commercial operation date: No developer press release or news article gives a COD for this project. The Cleanview solar listing says 'Expected online 2028', which is consistent with the LBNL date of 2028-04-01 but is an aggregator, not an independent signal. The Cleanview storage listing says 2027.
Developer: The LBNL developer field is null. Terra-Gen is inferred from the Sanborn project name and from Energy-Storage.News coverage of Terra-Gen's Kern County hybrid BESS permitting, but no source explicitly ties Terra-Gen to queue ID 1791. The news-extracted Terra-Gen fact comes from an article about the Lockhart CL I and II BESS (128.7 MW), which is a different project, so it was not used.
Status: LBNL shows active with an executed IA, and aggregator listings (Cleanview, interconnection.fyi, interxdata) still list it as planned or active. The news-extracted 'online' and 'COD achieved' signals concern the Lockhart BESS, not Sanborn 5 Hybrid, and were rejected as a project mismatch.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SANBORN 5 HYBRID project is a proposed energy storage project located in Kern County, California, within the CAISO region. The development project, with a total capacity of 574.89 MW, consists entirely of battery storage. The project is interconnected to the Windhub Substation at 230kV.
The project, identified as CAISO-1791 in the CAISO interconnection queue, entered the queue on April 15, 2020, and has a proposed commercial operation date of March 31, 2027. The interconnection agreement (IA) for the project has been executed. The utility is Southern California Edison (SCE).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ALTA6B2_7_N003
- POI Substation
- Windhub Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSolar queue pipeline by status
Data tables and metrics from the InfraSure database.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.