OVERNIGHT SOLAR
300 MW hybrid in San Bernardino, CA · In queue since April 2020 · Proposed COD November 2026
300 MW
Capacity
2
Components
Solar + Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Feb 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 10m
IA → COD
2y 9m
Total Duration
3y 10m
Schedule
0 months past proposed COD
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 18–30 months
Proposed COD: 2026-11-13
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
San Bernardino County Final Environmental Impact Report published
lus.sbcounty.govExpected online date per interconnection queue
cleanview.coResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ceqanet.lci.ca.gov/2024010434
- lus.sbcounty.gov/wp-content/uploads/sites/48/Overnight-Solar-FEIR.pdf
- downloads.regulations.gov/FWS-R8-ES-2024-0160-0003/content.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/california/1774_storage/overnight-solar
- aterio.io/insights/us-energy-projects/ep/overnight-solar-project
Commercial operation date: LBNL queue shows proposed COD of 2027-05-01. San Bernardino County FEIR (Oct 2024) confirms project is in environmental review phase, consistent with 2027 timeline. No contradictory developer announcements found.
Developer: LBNL filing entity is 'Overnight Solar LLC'. San Bernardino County environmental documents and USFWS Habitat Conservation Plan both identify applicant/owner as 'Overnight Solar LLC'. No parent company or operating entity identified in available sources.
Status: LBNL shows IA executed 2024-02-17 with active status. San Bernardino County published Final EIR in October 2024, and USFWS Habitat Conservation Plan is under federal review, indicating project is advancing through permitting.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
OVERNIGHT SOLAR is a proposed hybrid solar and battery project located in San Bernardino County, California, with a total capacity of 300 MW. The project consists of 150 MW of solar generation and a 150 MW battery energy storage system. It is listed in the CAISO interconnection queue as entry CAISO-1774, with a queue entry date of April 15, 2020, and a proposed commercial operation date of May 1, 2027. The project's point of interconnection is the Kramer Substation 230kV, and the interconnecting utility is Southern California Edison (SCE).
The project's interconnection agreement (IA) has been executed as of February 17, 2024. Recent news coverage indicates interest in the project, with nine articles appearing in industry publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Kramer Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LCKHT1_7_N001
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-07-11
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Overnight Solar
Data-driven briefing on Overnight Solar — fleet, generation, financial, and news signals.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.