ROADHOUSE STORAGE
312.96 MW storage in San Bernardino, CA · In queue since April 2020 · Proposed COD June 2027
312.96 MW
Capacity
1
Components
Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Jan 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
IA → COD
4y 5m
Total Duration
2y 9m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-12
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
medium confidence at research time
- project.nexteraenergyresources.com/roadhouse-energy-storage
- ceqanet.lci.ca.gov/2022100425/4
- cleanview.co/power-projects/planned/battery-storage-projects/california/1768_storage/roadhouse-storage
- cleanview.co/power-projects/planned/battery-storage-projects/california/70238_RDHS/roadhouse-energy-center
- interconnection.fyi/project/caiso-1768
- energy-storage.news/nextera-to-build-600mw-bess-in-san-bernadino-county-california-half-of-capacity-contracted-to-utility-apu/
Commercial operation date: LBNL proposed COD is 2027-06-12. Cleanview says 'Expected online 2027' for Roadhouse Storage and December 2027 for the Roadhouse Energy Center listing. Both are aggregator sources, and they are within a year of LBNL, so there is no meaningful disagreement.
Developer: The LBNL developer field is null. The CEQA record names Roadhouse Energy Storage, LLC as applicant, 'a wholly-owned indirect subsidiary of NextEra Energy Resources', and NextEra hosts the project website. The LLC name comes from the CEQA record, not the LBNL filing.
Status: LBNL shows IA Executed with active status, and the NextEra site and CEQA record describe the project as 'proposed', which is consistent with that. No source reports groundbreaking, construction or operation.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Roadhouse Storage project is a proposed 312.96 MW battery storage project located in San Bernardino County, California. The project is interconnected to the CAISO grid via the Mira Loma Substation 230kV and is in the CAISO interconnection queue as entry CAISO-1768, with a queue entry date of April 15, 2020. The proposed commercial operation date is June 12, 2027, and the Interconnection Agreement has been executed.
The Roadhouse Storage project is actively listed in the CAISO queue and has been the subject of recent news coverage related to deals, development, and regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Mira Loma Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MIRALOMA_6_N001
- POI Substation
- Mira Loma Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBattery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.