COMMERCE ENERGY STORAGE 2
250 MW storage in Los Angeles, CA · In queue since April 2020 · Proposed COD March 2026
250 MW
Capacity
1
Components
Battery
6y 3m
In Queue
System Impact Study
IA Phase
Signed Jan 2023
Queue → IA
2y 9m
IA → COD
3y 2m
Total Duration
2y 9m
Schedule
4 months past proposed COD
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-15
The Commerce Energy Storage 2 project is a proposed 250 MW battery storage project located in Los Angeles County, California. The project is in the CAISO interconnection queue (CAISO-1766) with a queue entry date of April 15, 2020, and a proposed commercial operation date of March 15, 2026. The project's interconnection status is currently in the System Impact Study phase, with the study initiated on January 31, 2023. The point of interconnection is the Laguna Bell Substation at 230kV, and the utility is Southern California Edison (SCE).
The development project has been the subject of recent news coverage, with 12 articles appearing in the press. These articles cover topics such as deals, industry trends, project development, and regulatory matters.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Laguna Bell Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAGUBELL_6_N005
- POI Substation
- Laguna Bell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about COMMERCE ENERGY STORAGE 2Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.