SAPPHIRE SOLAR
234 MW hybrid in Riverside, CA · In queue since April 2020 · Proposed COD December 2034
234 MW
Capacity
2
Components
Solar + Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Mar 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 11m
IA → COD
10y 9m
Total Duration
3y 11m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 18–30 months
Proposed COD: 2034-12-31
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
PPA with SCPPA terminated due to rising costs
energy-storage.newsResearch sources and reasoning (5 recorded sources)
high confidence at research time
- energy-storage.news/solar-storage-ppa-between-edf-southern-california-public-power-authority-scrapped-over-rising-costs/
- saurenergy.com/solar-energy-news/edf-renewables-to-supply-117-mwac-of-solar-energy-to-california-utility
- edf-re.com/project/sapphire-solar-project/
- ceqanet.lci.ca.gov/2023050303
- pv-tech.org/edf-renewables-signs-117mw-californian-ppa-with-state-power-authority/
Commercial operation date: LBNL shows 2034-12-31 proposed COD, but this appears to be a placeholder date. No news sources provide an updated COD target. The PPA was terminated in April 2025 per Energy-Storage.News, suggesting the project timeline is now uncertain.
Developer: News sources and EDF's own project page confirm EDF Renewables North America as the operating developer. CEQA filing shows 'Sapphire Solar, LLC' as the legal applicant entity, which is the project-specific LLC.
Status: Energy-Storage.News reported April 3, 2025 that the PPA between EDF and Southern California Public Power Authority was scrapped over rising costs. While LBNL shows 'active' with IA executed, the loss of the sole announced offtaker effectively cancels commercial viability unless a new PPA is secured.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Sapphire Solar project is a proposed 243.29 MW hybrid solar and battery energy storage project located in Riverside County, California. The development project consists of a 126.29 MW solar component and a 117 MW battery energy storage system. It is interconnected to the CAISO grid at the Red Bluff Substation 230kV and is in the CAISO interconnection queue as entry CAISO-1764, with a queue entry date of April 15, 2020. The project's proposed commercial operation date is December 31, 2034, and the Interconnection Agreement (IA) has been executed.
The Sapphire Solar project has been the subject of recent news coverage, with six articles categorized as regulatory (3), deals (2), and industry (1).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Red Bluff Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OBERON_7_N122
- POI Substation
- Red Bluff Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
SAPPHIRE SOLAR
Data-driven briefing on Sapphire Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.