GRACE ENERGY CENTER
1,017.12 MW hybrid in Riverside, CA · In queue since April 2020 · Proposed COD January 2027
1,017.12 MW
Capacity
2
Components
Solar + Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed May 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 1m
IA → COD
3y 8m
Total Duration
3y 1m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 18–30 months
Proposed COD: 2027-01-13
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/california/1761_photovoltaic/grace-energy-center
- ceqanet.lci.ca.gov/2025010194/2
- aqmd.gov/docs/default-source/ceqa/comment-letters/2026/march-2026/odp260218-04-seir-grace-solar-energy-center-project.pdf?sfvrsn=84c6687e_3
- interconnection.fyi/eia/plant/69820
Commercial operation date: The South Coast AQMD EIR comment letter says "Construction is expected to take 28 months with operation starting as early as 2027," and Cleanview also lists "Expected online 2027," which matches the LBNL date of 2027-01-13. Phase 2 (the BESS) was still in CEQA review in Feb-Mar 2026, so 2027 looks optimistic and could slip. The source is year-only because no source gives a firmer date.
Developer: LBNL lists no developer. interconnection.fyi (EIA data) names the operator as the shell entity Grace Orchard Interconnection, LLC, and no source identifies a parent. The news-extracted NextEra Energy attribution comes from a 2018 pv magazine article about Pinal Central Solar in Arizona, a different project, so I rejected it as a false match.
Status: LBNL shows the project as active with an executed IA. The CEQA record (Jan 2025 filing, Feb 2026 update) and the AQMD EIR comments show the project is still in environmental permitting, not construction.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Grace Energy Center is a proposed 1017.12 MW hybrid solar and battery project located in Riverside County, California. The development project consists of 508.56 MW of solar generation and 508.56 MW of battery energy storage. Interconnection is being pursued through the CAISO queue under queue ID CAISO-1761, with an interconnection request date of April 15, 2020, and a proposed commercial operation date of January 13, 2027. The project has an executed Interconnection Agreement (IA) with Southern California Edison (SCE).
The Grace Energy Center has been the subject of recent news coverage, with 18 articles categorized as industry-related and regulatory.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Colorado River Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesSolar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.