GRACE ENERGY CENTER
1,017.12 MW hybrid in Riverside, CA · In queue since April 2020 · Proposed COD January 2027
1,017.12 MW
Capacity
2
Components
Solar + Battery
6y 3m
In Queue
IA Executed
IA Phase
Signed May 2023
Queue → IA
3y 1m
IA → COD
3y 8m
Total Duration
3y 1m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-01-13
The Grace Energy Center is a proposed 1017.12 MW hybrid solar and battery project located in Riverside County, California. The development project consists of 508.56 MW of solar generation and 508.56 MW of battery energy storage. Interconnection is being pursued through the CAISO queue under queue ID CAISO-1761, with an interconnection request date of April 15, 2020, and a proposed commercial operation date of January 13, 2027. The project has an executed Interconnection Agreement (IA) with Southern California Edison (SCE).
The Grace Energy Center has been the subject of recent news coverage, with 18 articles categorized as industry-related and regulatory.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Colorado River Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.